()techniquesareusedtofindwaystobringprojectactivitiesthatarealignmentwiththeplanbyfasttrackingorcrashingtheschedulefortheremainingwork.
A.Schedule forecasts
B.Schedule compression
C.Change requests
D.Data analysis
正确答案是B