()istheapprovedversionofthetime-phasedprojectbudget,excludingany

分类: (中级) 系统集成项目管理工程师 发布时间: 2023-11-03 05:21 浏览量: 0

()istheapprovedversionofthetime-phasedprojectbudget,excludinganymanagementreserves,whichcanonlybechangedthroughformalchangecontrolpreceduresandisusedasabasisforcomparisontoactualresults.

A.The control accounts

B.Funding requirement

C.The cost estimates

D.The cost baseline

正确答案是D