()isthesumofallbudgetsestablishedfortheworktobeperformed.

分类: (中级) 系统集成项目管理工程师 发布时间: 2023-11-03 05:21 浏览量: 0

()isthesumofallbudgetsestablishedfortheworktobeperformed.

A.CPI

B.BAC

C.SPI

D.EAC

正确答案是B